GIS4043 Final Project and Presentation
For the final project, the assignment was to perform GIS analysis on a proposed FPL transmission corridor. The objective was to use ArcGIS Pro to quantify key parameters that are typically evaluated to determine the proposed corridor's impact on nearby homes, schools, land owners, and environmentally sensitive areas. The map results can be seen above.
Based on the evaluation, the transmission corridor has the following impacts:
No schools within corridor vicinity
43 homes within vicinity of corridor
255 parcels within vicinity of corridor
13.9% of the corridor is wetlands
163.4 Acres of conservation lands within corridor
For more information, a link to the final presentation with transcript can be found below: